Estimation: what the Scrum Guide requires and leaves open

The Scrum Guide gives sizing to the Developers and never mentions story points. How a team picks its unit and uses it.

One ticket, two numbers. Four cards at 5, two at 8, and the Planning Poker vote has been going for twenty minutes. The disagreement is about the unit, and nobody has reread the sentence in the Scrum Guide that says who owns sizing [1].

The guide gives sizing to the Developers

The Product Backlog is an ordered, emergent list of what is needed to improve the product [1]. On estimation, one sentence settles it: “The Developers who will be doing the work are responsible for the sizing.” The Product Owner may influence them by helping them understand and select trade-offs [1].

The guide stops there. Neither story points nor Planning Poker appear in it [1].

The word it uses is sizing, and the guide does not break it down. The distinction that follows comes from practice, and the guide never states it: sizing means comparing items with each other and checking that one of them fits in a Sprint; assigning a number means putting a figure on it, a figure that then serves to order, to split, to discuss a disagreement. A team can size without ever assigning numbers, by splitting until every item is visibly small. Nothing in the guide prevents that.

Sprint Planning asks for no total. The Sprint Backlog is made up of the Sprint Goal, the selected items, and a plan for delivering them [1]; no sum of points is required to validate the selection.

Write the unit on the board before the first vote

Take a team of six working with two reference stories: a contact form at 3, a login page at 5. Nobody remembers when those votes happened. A new joiner asks whether “5” means three days or a week; two people answer at the same time, with two different answers. The session ends without a single ticket estimated.

The move that prevents this fits on one line on the board, not in a file: “scale in ideal days, one uninterrupted day; reference: contact form = 3.” Anyone joining the vote reads the rule before picking up a card. Keep few references, two or three, enough to anchor the vote without consulting a conversion table.

An ideal-day scale accepts a starting value expressed in working days. Story points stay relative: Cohn describes them as a team-specific measure that does not convert to days [2]. Pinning “1 point = half a day” onto a story-point scale mixes the two, and a March vote no longer compares with a June vote. The costliest mistake is changing unit midstream: a team moving from story points to ideal days must recalibrate its references, or the old 5 and the new 5 no longer mean the same work. Re-estimating old tickets to “clean up” the backlog creates the same confusion, with no Increment in return.

Have everyone vote at the same time

Simultaneous voting stops the most senior opinion from becoming the group's answer. Cohn describes the mechanics of Planning Poker: each person places a card face down, all are turned over together, then the lowest and highest values are explained [2].

A common scene: six people, a database migration ticket, five cards at 3 and one at 13. The person who voted 13 sees a regression test that is missing and that nobody has written yet. Two minutes of explanation, a revote at 8, next ticket, and the team leaves with one more test in the Sprint.

The Product Owner who announces “I'd say 8” before the cards are turned over breaks the setup: the team hears an instruction and aligns, while the guide places sizing on the Developers' side [1]. The same effect occurs when the facilitator comments on their own card before the others. Aiming for unanimity produces a similar blockage: the revote checks that an argument has been heard, not to convert the person holding on to their 13. For a remote vote, the Planning Poker tool from Agile Workshop replaces the card deck.

Use the numbers to talk, not to promise

A number serves to split and to order. It becomes a promise as soon as it leaves the team and enters a management commitment. From that moment, the team learns to overestimate: the 8 becomes 13 as a precaution, the discussion about real difficulty fades, and the number no longer measures much.

Velocity is a team measure, absent from the guide [1]. Kniberg describes teams that estimate in story points and others in ideal days [3]. Story points remain a relative measure, specific to the team that set them [2]: comparing two teams on that number is comparing two scales with no common zero. The unit matters less than its stability.

Another path exists, with no number placed on items. The Kanban Guide keeps four measures: Work in Progress, throughput, Work Item Age, and Cycle Time [4]. A throughput observed over a recent window, the last eight weeks for example, gives a delivery range; the length of that window is a team choice, which the guide does not settle [4]. The Agile Manifesto counts simplicity among its principles: “Simplicity, the art of maximizing the amount of work not done, is essential” [5].

When a date lands before the estimation

Take a team told at a Sprint Review that a production release is set for March 15. The Product Backlog holds forty items, of which only about ten have been looked at. The reflex is to schedule a three-hour session to estimate everything; it will produce a total that nobody will defend three weeks later.

We recommend answering with a delivery range drawn from throughput, then handing the scope decision back to the Product Owner. The Kanban Guide describes the Service Level Expectation for this: a service-level expectation expressed as a probability on Cycle Time, such as “85% of items finished in eight days or less” [4]. It is expressed on observed Cycle Time, not on a hunch in the room. The two tools complement each other: the throughput range gives a deliverable volume over a period, the SLE a time commitment per item.

The useful next move: ask the Product Owner to choose what drops out. A fixed date with an open scope remains tenable; the reverse produces Sprint endings where half is delivered and the rest is renegotiated.

Split rather than estimate finely

An item that takes three days gets cut in two before entering a Sprint. That is a practice recommendation: the guide sets no item size, and splitting does more for forecasting than a notch of precision gained on the scale.

The test we suggest takes thirty seconds: two people look at the item and say whether or not it fits in half a Sprint. If they hesitate, the item is too big, and no vote will fix that. Some teams skip this entirely and steer by flow, splitting daily; that assumes a board kept up to date, so a discipline that does not improvise itself.

One question remains to be settled collectively, and it comes back at every planning session: who writes the unit and the reference on the board, before the first card is placed?

Sources

  1. Ken Schwaber et Jeff Sutherland, The Scrum Guide, novembre 2020.
  2. Mike Cohn, Prentice Hall, Agile Estimating and Planning, 2005-11.
  3. Henrik Kniberg, InfoQ, Scrum and XP from the Trenches, 2015-01.
  4. Daniel Vacanti & John Coleman, The Kanban Guide, 2021-02.
  5. Agile Manifesto, Manifeste pour le développement agile de logiciels, 2001-02.